Friday, July 22, 2022

July 20 2022

                                         Daily Job Report


Fincon -  12 Worker's

Work on patching interior bldg B & building C, strip east dumpster enclosures on bldg C, finish columns & headers on T.I., work on drain trenches  & clean up.

U.I.S Paint - 3 Worker's

Work on painting bldg B interior & clean up

Highmark Elec - 2 Worker's

Work on bldg C & B interior power & clean up

ESP Excavation - 3  workers

Rough grade on west & north ponds, grade docks, move extra dirt, layout & clean up

Capitol Glass - 4 Worker's

Work on window frames in building B, layout & clean up

Industrial Door - 1 Worker

Work on overhead doors, load move & unload material, layout & clean up

            Weather -  Sunny  - High 102  Low 70



















No comments:

Post a Comment

December 13 2022