Tuesday, August 2, 2022

Aug 2 2022

                                             Daily Job Report


Fincon -  14 Worker's

Work on patching interior bldg C, work on dock & dumpster enclosure walls, clean forms, layout on T.I., work on drain's & trenches  & clean up.

Highmark Elec - 2 Worker's

Work on bldg B interior power & lights, clean up

U.I.S Paint - 2 Worker's

Work on painting bldg B exterior & clean up

Canvis Drywall- 2 Worker's

Hang sheetrock on bathroom & Closet's bldg B & clean up

ESP Excavation - 3  workers

Work on final grade on docks & ponds, layout & clean up

Kimco - 2 Worker's

Work on fire lines in building C, load move & unload material, layout & clean up

Steerling Structures - 6 Workers

Work on framing the north end of T.I.

            Weather - Cloudy & Rain - High 88  Low 70





















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...