Thursday, August 4, 2022

August 3 2022

                                              Daily Job Report


Fincon -  14 Worker's

Work on patching interior bldg C, work on dock & dumpster enclosure walls, clean forms, layout on T.I., work on drain's & trenches  & clean up.

Highmark Elec - 2 Worker's

Work on bldg B interior power & lights, clean up

U.I.S Paint - 2 Worker's

Work on painting bldg B exterior & clean up

ESP Excavation - 2  workers

Work on final grade on docks & ponds, layout & clean up

Steerling Structures - 6 Workers

Work on framing the north end of T.I.

            Weather - Partly Cloudy - High 98  Low 70