Monday, August 22, 2022

August 17 2022

                                              Daily Job Report


Fincon -  10 Worker's

Work on saw cutting footings for bldg B T.I., finish install on wall heaters, move forms,, layout on T.I., work on floors, unload handrails  & clean up.

Highmark Elec - 2 Worker's

Work on bldg C interior power & clean up

U.I.S Paint - 1 Worker

Work on painting bldg B blue striping west side & clean up

ESP Excavation - 3  workers

work on final grade on dock paving, layout & clean up

Capitol Glass - 2 Worker's

Work on window's in building B, layout & clean up

Kimco - 2 Worker's

Work on fire lines in building C, load move & unload material, layout & clean up

Steerling Structures - 6 Workers

Work on framing the office area and set ceiling framing on T.I. & clean up

            Weather - Sunny & Hot - High 96  Low 70