Daily Job Report
Fincon - 10 Worker's
Finish up patching interior bldg C, work on saw cutting footings for bldg B T.I., install heaters, move forms,, layout on T.I., work on floors & clean up.
Finish up patching interior bldg C, work on saw cutting footings for bldg B T.I., install heaters, move forms,, layout on T.I., work on floors & clean up.
Highmark Elec - 2 Worker's
Highmark Elec - 2 Worker's
Work on bldg C intrior power & clean up
Work on bldg C intrior power & clean up
U.I.S Paint - 1 Worker
U.I.S Paint - 1 Worker
Work on painting bldg B blue striping west side & clean up
Work on painting bldg B blue striping west side & clean up
ESP Excavation - 3 workers
ESP Excavation - 3 workers
work on final grade on dock paving, layout & clean up
work on final grade on dock paving, layout & clean up
Capitol Glass - 2 Worker's
Capitol Glass - 2 Worker's
Work on window's in building B, layout & clean up
Work on window's in building B, layout & clean up
Kimco - 2 Worker's
Kimco - 2 Worker's
Work on fire lines in building C, load move & unload material, layout & clean up
Steerling Structures - 6 Workers
Work on framing the office area and set ceiling framing on T.I. & clean up
Work on fire lines in building C, load move & unload material, layout & clean up
Steerling Structures - 6 Workers
Work on framing the office area and set ceiling framing on T.I. & clean up
Weather - Sunny & Hot - High 94 Low 70