Daily Job Report
Fincon - 6 Worker's
Pour dock paving, work on saw cutting footings for bldg B T.I., move forms,, layout on T.I & east retaining wall, work on floors, layout handrails & clean up.
Pour dock paving, work on saw cutting footings for bldg B T.I., move forms,, layout on T.I & east retaining wall, work on floors, layout handrails & clean up.
Highmark Elec - 2 Worker's
Highmark Elec - 2 Worker's
Work on bldg B & C interior power, pull main wire to panels & clean up
Work on bldg B & C interior power, pull main wire to panels & clean up
U.I.S Paint - 2 Worker's
U.I.S Paint - 2 Worker's
Work on painting bldg B blue striping west side & clean up
Work on painting bldg B blue striping west side & clean up
ESP Excavation - 3 workers
ESP Excavation - 3 workers
work on final grade on dock paving, layout & clean up
work on final grade on dock paving, layout & clean up
Capitol Glass - 2 Worker's
Capitol Glass - 2 Worker's
Work on window's in building B, layout & clean up
Work on window's in building B, layout & clean up
Kimco - 2 Worker's
Kimco - 2 Worker's
Work on fire lines in building C & B, load move & unload material, layout & clean up
Steerling Structures - 6 Workers
Work on framing the office area and set ceiling framing on T.I. & clean up
Rocky Mnt Power - 6 Workers
Pull main power wires, set ground sleeves & transformers & clean up
Work on fire lines in building C & B, load move & unload material, layout & clean up
Steerling Structures - 6 Workers
Work on framing the office area and set ceiling framing on T.I. & clean up
Rocky Mnt Power - 6 Workers
Pull main power wires, set ground sleeves & transformers & clean up
Weather - Cloudy - High 81 Low 64