Monday, August 22, 2022

August 19 2022

                                                Daily Job Report


Fincon -  6 Worker's

Pour dock paving, work on saw cutting footings for bldg B T.I., move forms,, layout on T.I & east retaining wall, work on floors, layout handrails  & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power, pull main wire to panels & clean up

U.I.S Paint - 2 Worker's

Work on painting bldg B blue striping west side & clean up

ESP Excavation - 3  workers

work on final grade on dock paving, layout & clean up

Capitol Glass - 2 Worker's

Work on window's in building B, layout & clean up

Kimco - 2 Worker's

Work on fire lines in building C & B, load move & unload material, layout & clean up

Steerling Structures - 6 Workers

Work on framing the office area and set ceiling framing on T.I. & clean up

Rocky Mnt Power - 6 Workers

Pull main power wires, set ground sleeves & transformers & clean up

            Weather - Cloudy - High 81  Low 64


























No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...