Monday, August 22, 2022

August 22 2022

                                                 Daily Job Report


Fincon -  6 Worker's

Pour dock paving & finish, layout on T.I & east retaining wall, work on floors, clean up framing area & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power, work on main wire to panels & clean up

U.I.S Paint - 2 Worker's

Work on painting bldg B blue striping west side & clean up

Capitol Glass - 2 Worker's

Work on the window's in building B, layout & clean up

Steerling Structures - 3 Workers

Work on framing the office area & clean up


            Weather - Sunny - High 91  Low 68











No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...