Friday, August 26, 2022

August 25 2022

                                                  Daily Job Report


Fincon -  14 Worker's

Pour dock paving, dig out footings & plumbing treches for bldg B T.I., move forms,, layout on T.I & pour east retaining wall footings, work on floors, layout handrails  & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power & clean up

Horizon Plumbing - 2  workers

Work on interior rough in on Bldg C T.I., layout & clean up

Capitol Glass - 2 Worker's

Work on window's in building B, layout & clean up

ESP Excavation - 3  workers

Rough grade on curb & gutter, grade dock waterway, move extra dirt, layout & clean up


            Weather - Sunny - High 92  Low 64