Friday, August 26, 2022

August 26 2022

                                                   Daily Job Report


Fincon -  10 Worker's

Work on digging out footings & plumbing trenches for bldg B, T.I., move forms,, layout on T.I & strip east retaining wall footings, work on floors, layout handrails  & clean up.

Highmark Elec - 1 Worker

Work on bldg B & C interior power & clean up

Capitol Glass - 2 Worker's

Work on window's in building B, layout & clean up

ESP Excavation - 3  workers

Rough grade on curb & gutter, grade dock waterway, move extra dirt, layout & clean up


            Weather - Sunny - High 92  Low 64