Tuesday, August 30, 2022

August 30 2022

                                                     Daily Job Report


Fincon -  12 Worker's

Work on east retaining wall, work on floors, install rebar in building B, T.I. layout handrails, set dumpster gates & weld & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power & clean up

Capitol Glass - 1 Worker

Work on the window's in building B, layout & clean up

Horizon Plumbing -  3 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building B & clean up

ESP Excavation - 3  workers

Work on grading curb & gutter, work on dock paving, layout & clean up



            Weather - Sunny - High 98  Low 64