Tuesday, August 30, 2022

August 29 2022

                                                    Daily Job Report


Fincon -  12 Worker's

Finish digging out footings & plumbing trenches for bldg B, T.I., move forms,, layout on T.I & set retaining wall footings, work on floors, layout handrails, finish pouring dock ramps & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power & clean up

Capitol Glass - 2 Worker's

Work on the window's in building B, layout & clean up

Horizon Plumbing -  3 worker's

Work on interior rough in on Bldg C T.I., layout gas lines and start in building B & clean up

Arbon - 2 Worker's

Work on the dock levlers in building B, layout & clean up



            Weather - Sunny - High 95  Low 64