Daily Job Report
Fincon - 10 Worker's
Work on patching interior bldg B, work on dock & dumpster enclosure walls, clean forms,, layout on T.I., work on drain trenches & clean up.
Work on patching interior bldg B, work on dock & dumpster enclosure walls, clean forms,, layout on T.I., work on drain trenches & clean up.
Highmark Elec - 2 Worker's
Highmark Elec - 2 Worker's
Work on bldg C intrior power & clean up
Work on bldg C intrior power & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Work on drains and underground in T.I. Bldg C, layout & clean up
Work on drains and underground in T.I. Bldg C, layout & clean up
U.I.S Paint - 3 Worker's
U.I.S Paint - 3 Worker's
Work on painting bldg B interior & clean up
Work on painting bldg B interior & clean up
ESP Excavation - 3 workers
ESP Excavation - 3 workers
Rough grade on west & north ponds, grade docks, move extra dirt, layout & clean up
Rough grade on west & north ponds, grade docks, move extra dirt, layout & clean up
Capitol Glass - 2 Worker's
Capitol Glass - 2 Worker's
Work on window frames in building B, layout & clean upIndustrial Door - 1 Worker
Work on window frames in building B, layout & clean up
Industrial Door - 1 Worker
Work on overhead doors, load move & unload material, layout & clean up
Work on overhead doors, load move & unload material, layout & clean up
Kimco - 4 Worker's
Kimco - 4 Worker's
Work on fire lines in building C, load move & unload material, layout & clean up
Steerling Structures - 6 Workers
Work on framing north end of T.I.
Work on fire lines in building C, load move & unload material, layout & clean up
Steerling Structures - 6 Workers
Work on framing north end of T.I.
Weather - Sunny - High 101 Low 70





No comments: