July 29 2022

                                            Daily Job Report


Fincon -  4 Worker's

Work on patching interior bldg B, work on dock & dumpster enclosure walls, clean forms,, layout on T.I., work on drain trenches  & clean up.

Highmark Elec - 2 Worker's

Work on bldg C intrior power & clean up

U.I.S Paint - 2 Worker's

Work on painting bldg B interior & clean up

ESP Excavation - 3  workers

Rough grade on west & north ponds, grade docks, move extra dirt, layout & clean up

Capitol Glass - 2 Worker's

Work on window frames in building B, layout & clean up
Industrial Door - 1 Worker

Work on overhead doors, load move & unload material, layout & clean up

Kimco - 4 Worker's

Work on fire lines in building C, load move & unload material, layout & clean up

Steerling Structures - 6 Workers

Work on framing north end of T.I.

            Weather -  Sunny  - High 101  Low 70