Daily Job Report
Fincon - 5 Worker's
Finish doors in East T.I., work on backing & framing, clean out docks, move conex's, scrub floors, work on east retaining wall & clean up.
Finish doors in East T.I., work on backing & framing, clean out docks, move conex's, scrub floors, work on east retaining wall & clean up.
Highmark Elec - 1 Worker
Highmark Elec - 1 Worker
Work on bldg C interior T.I. power & clean up
Work on bldg C interior T.I. power & clean up
Horizon Plumbing - 3 worker's
Horizon Plumbing - 3 worker's
Work on interior rough in on Bldg C T.I., & clean up
Work on interior rough in on Bldg C T.I., & clean up
ESP Excavation - 4 workers
ESP Excavation - 4 workers
Work on grading curb & gutter, work on dock paving, layout & clean up
Work on grading curb & gutter, work on dock paving, layout & clean up
Kimco - 2 Worker's
Kimco - 2 Worker's
Work on fire sprinkler & clean up
Quality Fire - 2 Worker's
Work on fire sprinkler & clean up
Quality Fire - 2 Worker's
Work on fire alarms & strobes & clean up
Work on fire alarms & strobes & clean up