                                                         Daily Job Report


Fincon -  5 Worker's

Finish doors in East T.I., work on backing & framing, clean out docks, move conex's, scrub floors, work on east retaining wall & clean up.

Highmark Elec - 1 Worker

Work on bldg C interior T.I. power & clean up

Quiqksilver -  3 worker's

Work on setting up for curb & gutter & clean up

ESP Excavation - 4  workers

Work on grading curb & gutter, work on dock paving, layout & clean up

Kimco - 2 Worker's

Work on fire sprinkler building B & clean up

Quality Fire - 2 Worker's

Work on fire alarms & strobes & clean up

UIS Paint - 2 Worker's

Work on east building west wall interior & clean up