Tuesday, September 20, 2022

September 20 2022

                   Daily Job Report


Fincon -  8 Worker's

Work on painting dumpster enclosure doors, install expansion joint on dock paving, move material, work on T.I. & clean up.

Quiqksilver -  8 workers

Work on tie-in's pouring finishing curb & gutter & clean up

ESP Excavation - 4  workers

Work on grading curb & gutter, work on dock paving, layout & clean up

Kimco - 2 Worker's

Work on fire sprinkler building B & clean up

Pro HVAC - 2 Worker's

Work on roof cuts in east building T.I. & clean up


Industrial Door - 2 Worker's

Work on East building overhead doors & clean up

UIS Paint - 2 Worker's

Work on the south side exterior of the east building & clean up

            Weather - Sunny - High 86  Low 57