Tuesday, September 20, 2022

September 19 2022

                                    Daily Job Report


Fincon -  5 Worker's

Start painting dumpster enclosure doors, install expansion joint on dock paving, move material, work on T.I. & clean up.

Quiqksilver -  12 workers

Work on pouring & finishing curb & gutter & clean up

ESP Excavation - 4  workers

Work on grading curb & gutter, work on dock paving, layout & clean up

Kimco - 2 Worker's

Work on fire sprinkler building B & clean up

Industrial Door - 2 Worker's

Start on East building overhead doors & clean up

UIS Paint - 2 Worker's

Finish east building west wall interior, start on south side exterior of east building & clean up

            Weather - Sunny - High 86  Low 57