Tuesday, October 18, 2022

October 17 2022

                                             Daily Job Report


Fincon -  15 Worker's

Finish stucco east dumpster enclosures, set forms, pour & finish final approach on the east side, move material, clean up docks, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the east parking lot, compact, layout & clean up

Capitol Glass - 2 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C & B walls & clean up

Highmark Electric- 1 Worker

Work on main power both building's & clean up

Horizon Plumbing -  2 worker's

Work on interior rough in on Bldg C T.I., finish gas lines & in building C, work on air lines & clean up

Industrial Doors -  1 worker

Finish up overhead doors in on Bldg C & clean up

                     Weather - Sunny - High 74  Low 42