Tuesday, October 18, 2022

October 14 2022

                                                     Daily Job Report


Fincon -  15 Worker's

Stucco east dumpster enclosures, set forms, move material, clean up docks, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the east parking lot, compact, layout & clean up

Capitol Glass - 2 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C & B walls & clean up

PRO HVAC - 2 Worker's

Work on ductwork in east building T.I., start on venting heaters in building B & clean up

Highmark Electric- 2 Worker's

Work on main power to east building & clean up


Industrial Doors -  1 worker

Work on overhead doors in on Bldg C & clean up

                     Weather - Sunny - High 74  Low 42