Tuesday, October 11, 2022

October 11 2022

                                                   Daily Job Report


Fincon -  6 Worker's

Stucco east retaining wall, work on bollards, move material, clean up docks, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the west parking lot, compact, layout & clean up

Capitol Glass - 2 Worker's

Work on east building, north wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C east walls & clean up

PRO HVAC - 2 Worker's

Work on ductwork in east building T.I. & clean up

Horizon Plumbing -  2 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up


                  Weather - Sunny - High 74  Low 46