Monday, October 10, 2022

October 10 2022

                                                  Daily Job Report


Fincon -  16 Worker's

Stucco dock walls, work on bollards, pour & finish north paving, cut concrete, move material, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the parking lot, work on sidewalks, compact, cut concrete, layout & clean up

Capitol Glass - 2 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C east walls & clean up

PRO HVAC - 2 Worker's

Work on ductwork in east building T.I. & clean up

Horizon Plumbing -  2 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up


                  Weather - Sunny - High 76  Low 46