Monday, October 10, 2022

October 7 2022

                                                  Daily Job Report


Fincon -  6 Worker's

Stucco dock walls, work on inlet box's, move material, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the parking lot, work on sidewalks, compact, cut concrete, layout & clean up

Capitol Glass - 2 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C east walls & clean up

PRO HVAC - 2 Worker's

Work on ductwork in east building T.I. & clean up


                  Weather - Sunny - High 76  Low 46








No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...