                                                 Daily Job Report


Fincon -  4 Worker's

Work on framing & backing, bollards, caulk paving, layout, work on cleanouts in the floor, move material & clean up.

Capitol Glass - 4 Worker's

Work on east & west building's finish setting frames, set glass & clean up

UIS Paint - 1 Worker

Work on Bldg B interior walls & clean up

Kimco - 3 Worker's

Work on fire lines in east T.I. & clean up

Steerling Structures - 2 Worker's

Finish up framing & demising wall on west T.I. & clean up

Pro Heating & Air    -  2 Workers

Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up

            Weather - Cloudy Cold - High 45  Low 21