Daily Job Report
Fincon - 2 Worker's
Work on framing & backing, install windows in production rooms, move material & clean up.
Work on framing & backing, install windows in production rooms, move material & clean up.
Capitol Glass - 2 Worker's
Capitol Glass - 2 Worker's
Work on east & west building's finish setting frames, set glass & clean up
Canvis Drywall - 8 Workers
Work on hanging sheetrock from north to south & unload material & clean up
Work on east & west building's finish setting frames, set glass & clean up
Canvis Drywall - 8 Workers
Work on hanging sheetrock from north to south & unload material & clean up
Kimco - 2 Worker's
Kimco - 2 Worker's
Work on fire lines in east T.I. & clean up
Pro Heating & Air - 2 Workers
Work on fire lines in east T.I. & clean up
Pro Heating & Air - 2 Workers
Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up
Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up