Wednesday, November 9, 2022

November 4 2022

                                               Daily Job Report


Fincon -  4 Worker's

Hang exterior mandoorscaulk paving, paint structural steel for west building T.I., layout, move material, clean up docks, cut concrete & clean up.

Capitol Glass - 4 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg B walls & clean up

Highmark Electric- 2 Worker's

Work on power & lights B building & clean up


Pro Heating & Air    -  2 Workers

Install duct work on both build-outs, work on wall heaters, unload material & clean up

               Weather - Cloudy - High 54  Low 32