Thursday, November 3, 2022

October 18 - November 3 - 2022

                                              Daily Job Report


Fincon -  6 Worker's

Hang exterior mandoors, caulk paving, seal west building floor, hang structural steel for west building T.I., pour & finish concrete in west T.I., primer structural steel, move material, clean up docks, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the parking lot's for asphalt, layout & clean up

Capitol Glass - 4 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C & B walls & clean up

Highmark Electric- 2 Worker's

Work on power & lights in both buildings & clean up

Horizon Plumbing -  2 workers

Work on interior rough in on Bldg C T.I., work on air lines & drain lines, unload material & clean up

Geneva Rock 

Asphthe alt parking lots & clean up

Rocky Mnt Stripping - 2 Workers

Stripe Parking lot & Clean up

Pro Heating & Air    -  2 Workers

Install duct work on both build-outs, work on wall heaters, unload material & clean up










































































                     

No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...