Monday, December 5, 2022

December 2 2022

                                                   Daily Job Report


Fincon -  4 Worker's

Work on center bathroom buildout on building B, Rubber base, frp, trim, doors, plastic & plywood up missing windows in east building, move material & clean up.

Capitol Glass - 4 Worker's

Work on the east building, set glass & caulking & clean up

Pro Heating & Air    -  2 Workers

Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up

Canvis Drywall  -  8 Workers

Work on hanging sheetrock from north to south in east T.I. & unload material & clean up

UIS Paint - 1 Worker

Work on exterior walls & clean up

Highmark Elec - 1 Worker

Work on east T.I., work on center buildout on west building & clean up


Kimco - 2 Worker's

Work on fire lines in east T.I. & clean up


            Weather - Cloudy - High 40  Low 30










































No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...