                                                   Daily Job Report


Fincon -  4 Worker's

Work on framing & backing, hang doors on center bathroom, work on floors, cover missing windows, move material & clean up.

Capitol Glass - 4 Worker's

Work on east building doors & clean up

Horizon Plumbing - 2 Worker's

Work on plumbing on west bldg center bathroom area & Nutricost buildout & clean up

Pro Heating & Air    -  2 Workers

Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up

Canvis Drywall  -  4 Workers

Work on hanging sheetrock & unload material & clean up

Advanced Roofing - 3 Worker's

Work on roof cap building C & clean up

Kimco - 2 Worker's

Work on fire lines in east T.I. production rooms & clean up


            Weather - Snow & Cloudy - High 34  Low30


























 