                                Daily Job Report


Fincon -  16 Worker's

Strip footings & dock walls, work on patching building B, pour 5 dock walls on bldg c, weld panel corners & lap panels, clean floors & clean up.

 Wasatch  - 4 Worker's
Work on bracing & angels, install roof frame drains & clean up



 Weather -  Cloudy & Rain  - High 58   Low 44

















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...