Friday, April 1, 2022

March 30 2022

                                 Daily Job Report


Fincon -  16 Worker's

Strip footings & dock walls, work on patching building B, work on dock walls both blds, work on footings, layout, clean floors & clean up.

 Wasatch  - 4 Worker's
Work on bracing & angels, start the installation of decking & clean up

ESP Excavation - 1 Worker

Work on sewer east side, layout & clean up


            Weather -  Cloudy & Rain Early  - High 53   Low 33