Friday, April 1, 2022

April 1 2022

                                   Daily Job Report


Fincon -  16 Worker's

Strip & set dock walls, work on patching building B, work on dock wall footings, layout & clean up.

 Wasatch  - 6 Worker's
Work on bracing, angels & the installation of decking & clean up

ESP Excavation - 1 Worker

Finish sewer east side, backfill & compact, dig dock footings, layout & clean up


            Weather -  Sunny   - High 55   Low 37