Daily Job Report
Fincon - 16 Worker's
Pour dock walls, work on patching building B, work on dock walls both blds, work on footings, layout, clean floors & clean up.
Pour dock walls, work on patching building B, work on dock walls both blds, work on footings, layout, clean floors & clean up.
Wasatch - 6 Worker'sWork on bracing, angels & the installation of decking & clean up
Wasatch - 6 Worker's
Work on bracing, angels & the installation of decking & clean up
ESP Excavation - 1 Worker
ESP Excavation - 1 Worker
Work on sewer east side, backfill & compact, layout & clean up
Work on sewer east side, backfill & compact, layout & clean up