Friday, April 1, 2022

March 31 2022

                                  Daily Job Report


Fincon -  16 Worker's

Pour dock walls, work on patching building B, work on dock walls both blds, work on footings, layout, clean floors & clean up.

 Wasatch  - 6 Worker's
Work on bracing, angels & the installation of decking & clean up

ESP Excavation - 1 Worker

Work on sewer east side, backfill & compact, layout & clean up


            Weather -  Cloudy   - High 53   Low 32






No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...