                                    Daily Job Report


Fincon -  16 Worker's

Strip & set dock walls, work on patching building B, work on dock wall footings, layout & clean up.

 Wasatch  - 3 Worker's
Work on bracing, angels & the installation of decking & clean up

ESP Excavation - 3 Worker's

Work on sewer laterals, backfill & compact dock walls, dig dock footings, layout & clean up