                                         Daily Job Report


Fincon -  10 Worker's

Pour remainig dock walls, work on patching building B, strip dock wall footings, layout & clean up.

 Wasatch  - 6 Worker's
Work on bracing, angels & the installation of decking, stand columns Bldg C & start lifting joist's, clean up

ESP Excavation - 4 Worker's

Work on sewer laterals to the dock side, backfill & compact, layout & clean up


            Weather -  Cloudy, Cold Snow   - High 39   Low 29