Daily Job Report
Fincon - 15 Worker's
Set dock walls, work on patching building B, pour dock wall footings, layout & clean up.
Set dock walls, work on patching building B, pour dock wall footings, layout & clean up.
Wasatch - 3 Worker'sWork on bracing, angels & the installation of decking, stand columns Bldg C & clean up
Wasatch - 3 Worker's
Work on bracing, angels & the installation of decking, stand columns Bldg C & clean up
ESP Excavation - 4 Worker's
ESP Excavation - 4 Worker's
Work on sewer main & laterals to the west side, backfill & compact, layout & clean up
Work on sewer main & laterals to the west side, backfill & compact, layout & clean up