Thursday, April 7, 2022

April 5 2022

                                     Daily Job Report


Fincon -  16 Worker's

Strip & set dock walls, work on patching building B, pour dock wall's & footings, layout & clean up.

 Wasatch  - 5 Worker's
Work on bracing, angels & the installation of decking, start sorting out iron for Bldg C & clean up

ESP Excavation - 3 Worker's

Work on sewer laterals, backfill & compact dock walls, dig dock footings, layout & clean up


            Weather -  Cloudy Cold, Rain   - High 38   Low 33