Daily Job Report
Fincon - 16 Worker's
Strip & set dock walls, work on patching building B, pour dock wall's & footings, layout & clean up.
Strip & set dock walls, work on patching building B, pour dock wall's & footings, layout & clean up.
Wasatch - 5 Worker'sWork on bracing, angels & the installation of decking, start sorting out iron for Bldg C & clean up
Wasatch - 5 Worker's
Work on bracing, angels & the installation of decking, start sorting out iron for Bldg C & clean up
ESP Excavation - 4 Worker's
ESP Excavation - 4 Worker's
Work on sewer laterals, backfill & compact dock walls, dig dock footings, layout & clean up
Work on sewer laterals, backfill & compact dock walls, dig dock footings, layout & clean up