                                       Daily Job Report


Fincon -  16 Worker's

Strip & set dock walls, work on patching building B, pour dock wall's & footings, layout & clean up.

 Wasatch  - 5 Worker's
Work on bracing, angels & the installation of decking, start sorting out iron for Bldg C & clean up

ESP Excavation - 4 Worker's

Work on sewer laterals, backfill & compact dock walls, dig dock footings, layout & clean up

ESP Excavation - 4 Worker's

Work on sewer laterals, backfill & compact dock walls, dig dock footings, layout & clean up

Horizon Plumbing - 2 Worker's

Install roof drains in Bldg B, layout & clean up