Daily Job Report
Fincon - 12 Worker's
Pour & finish pourbacks west side Bldg C , work on capping weld plates building B, install rebar in pourbacks, final patch on building B, start layout on buildout of bldg C, clean floors & saw cut
Pour & finish pourbacks west side Bldg C , work on capping weld plates building B, install rebar in pourbacks, final patch on building B, start layout on buildout of bldg C, clean floors & saw cut
ESP Excavation - 4 Worker'sWork on water mains east of buildings C, backfill, compact, layout, haul off material & clean up
ESP Excavation - 4 Worker's
Work on water mains east of buildings C, backfill, compact, layout, haul off material & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Work on cleanouts & hose bibs, water lines & clean up
Work on cleanouts & hose bibs, water lines & clean up
Advanced Roofing - 6 Worker's
Advanced Roofing - 6 Worker's
Finish up bldg C roof, load material & clean up
Finish up bldg C roof, load material & clean up
UIS Painting - 3 Worker's
UIS Painting - 3 Worker's
Work on interior Bldg B around 2' windows
Work on interior Bldg B around 2' windows