Thursday, August 11, 2022

August 10 2022

                                                Daily Job Report


Fincon -  4 Worker's

Caulk floors in Bldg B north half, work on patching interior bldg C, work on dock walls, clean forms, finish rebar in docks, move material, clean floors for caulking in building B  & clean up.

Highmark Elec - 2 Worker's

Work on bldg C interior power & buildout & clean up

ESP Excavation - 3  workers

Work on the rough grade for curb & gutter, move extra dirt, layout & clean up


U.I.S Paint - 2 Worker's

Work on bldg B west wall & clean up


Kimco - 2 Worker's

Work on fire lines in building C , load move & unload material, layout & clean up

Steerling Structures - 2 Workers

Work on framing & center of T.I.

            Weather -  Sunny  - High 92  Low 69











No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...