Daily Job Report
Fincon - 4 Worker's
Caulk floors in Bldg B north half, work on patching interior bldg C, work on dock walls, clean forms, finish rebar in docks, move material, clean floors for caulking in building B & clean up.
Caulk floors in Bldg B north half, work on patching interior bldg C, work on dock walls, clean forms, finish rebar in docks, move material, clean floors for caulking in building B & clean up.
Highmark Elec - 2 Worker's
Highmark Elec - 2 Worker's
Work on bldg C interior power & buildout & clean up
Work on bldg C interior power & buildout & clean up
ESP Excavation - 3 workers
ESP Excavation - 3 workers
Work on the rough grade for curb & gutter, move extra dirt, layout & clean up
Work on the rough grade for curb & gutter, move extra dirt, layout & clean up
U.I.S Paint - 2 Worker's
U.I.S Paint - 2 Worker's
Work on bldg B west wall & clean up
Work on bldg B west wall & clean up
Kimco - 2 Worker's
Kimco - 2 Worker's
Work on fire lines in building C , load move & unload material, layout & clean up
Steerling Structures - 2 Workers
Work on framing & center of T.I.
Work on fire lines in building C , load move & unload material, layout & clean up
Steerling Structures - 2 Workers
Work on framing & center of T.I.
Weather - Sunny - High 92 Low 69