Fincon - 4 Worker's
Start pouring dock ramps, work on patching interior bldg B, work on dock walls, clean forms, install rebar in docks, move material, clean floors for caulking in building B & clean up.
Start pouring dock ramps, work on patching interior bldg B, work on dock walls, clean forms, install rebar in docks, move material, clean floors for caulking in building B & clean up.
Highmark Elec - 2 Worker's
Highmark Elec - 2 Worker's
Work on bldg C interior power & buildout & clean up
Work on bldg C interior power & buildout & clean up
ESP Excavation - 3 workers
ESP Excavation - 3 workers
Start rough grade for curb & gutter, move extra dirt, layout & clean up
Start rough grade for curb & gutter, move extra dirt, layout & clean up
Capitol Glass - 4 Worker's
Capitol Glass - 4 Worker's
Work on window frames in building B, set glass on south end, layout & clean up
Work on window frames in building B, set glass on south end, layout & clean up
U.I.S Paint - 2 Worker's
U.I.S Paint - 2 Worker's
Work on bldg B west wall & clean up
Work on bldg B west wall & clean up
Kimco - 4 Worker's
Kimco - 4 Worker's
Work on fire lines in building C & B, load move & unload material, layout & clean up
Steerling Structures - 4 Workers
Work on upper floor framing & center of T.I.
Work on fire lines in building C & B, load move & unload material, layout & clean up
Steerling Structures - 4 Workers
Work on upper floor framing & center of T.I.