                                               Daily Job Report


Fincon -  4 Worker's

Start pouring dock ramps, work on patching interior bldg B, work on dock walls, clean forms, install rebar in docks, move material, clean floors for caulking in building B  & clean up.

Highmark Elec - 2 Worker's

Work on bldg C interior power & buildout & clean up

ESP Excavation - 3  workers

Start rough grade for curb & gutter, move extra dirt, layout & clean up

Capitol Glass - 4 Worker's

Work on window frames in building B, set glass on south end, layout & clean up

U.I.S Paint - 2 Worker's

Work on bldg B west wall & clean up


Kimco - 4 Worker's

Work on fire lines in building C & B, load move & unload material, layout & clean up

Steerling Structures - 4 Workers

Work on upper floor framing & center of T.I.

            Weather -  Sunny  - High 88  Low 69