Thursday, August 11, 2022

August 11 2022

                                             Daily Job Report


Fincon -  4 Worker's

Pour & finish south dock ramps, work on patching interior bldg B & C, move material, clean off extra floor caulking, clean floors for caulking in building B  & clean up.

Highmark Elec - 3 Worker's

Work on bldg C interior power & buildout & clean up

ESP Excavation - 2  workers

Start rough grade for curb & gutter, move extra dirt, layout & clean up

Kimco - 2 Worker's

Work on fire lines in buildings C & B, load move & unload material, layout & clean up

Steerling Structures - 6 Workers

Work on framing the center of the T.I.

            Weather -  Sunny  - High 91  Low 69