Friday, August 12, 2022

August 12 2022

                                              Daily Job Report


Fincon -  6 Worker's

Work on patching interior bldg B & C, move material, get ready for floor caulking on south half of bldg B, clean floors in building C  & clean up.

Highmark Elec - 2 Worker's

Work on bldg C interior power & buildout & clean up

ESP Excavation - 3  workers

Work on rough grade for curb & gutter, move extra dirt, compact, layout & clean up

Kimco - 2 Worker's

Work on fire lines in buildings C, load move & unload material, layout & clean up

Steerling Structures - 6 Workers

Work on framing the bathrooms & offices of the T.I.
Industrial Door - 1 Worker

Work on overhead doors, load move & unload material, layout & clean up

            Weather -  Sunny  - High 91  Low 64