Tuesday, August 16, 2022

August 15 2022

                                               Daily Job Report


Fincon -  6 Worker's

Work on patching interior bldg B & C, move material, layout office & footings in bldg B T.I., clean floors in building C  & clean up.

Highmark Elec - 2 Worker's

Work on bldg C interior power & buildout & clean up

ESP Excavation - 3  workers

Work on rough grade for paving, move extra dirt, compact, layout & clean up

Kimco - 2 Worker's

Work on fire lines in buildings C, load move & unload material, layout & clean up

Steerling Structures - 6 Workers

Work on framing the bathrooms & offices of the T.I.
U.I.S. Paint - 1 Worker

Work on west side of building B blue strip's, move & unload material, mask & clean up

            Weather -  Sunny  - High 91  Low 64



















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...