Thursday, August 4, 2022

August 4 2022

                                            Daily Job Report


Fincon -  10 Worker's

Work on patching interior bldg B, work on dock & dumpster enclosure walls, clean forms,, layout on T.I., pour & finish drain trenches, work on dock walls  & clean up.

Highmark Elec - 2 Worker's

Work on bldg C interior power & clean up

Horizon Plumbing - 2 Worker's

Work on drains and underground in T.I. Bldg C, layout & clean up

ESP Excavation - 3  workers

Grade on docks, layout & clean up

Capitol Glass - 2 Worker's

Work on window frames in building B, layout & clean up
Industrial Door - 1 Worker

Work on overhead doors, load move & unload material, layout & clean up

Steerling Structures - 6 Workers

Work on framing second floor on north end of T.I.

            Weather -  Sunny  - High 97  Low 70