Monday, August 8, 2022

August 5 2022

                                             Daily Job Report


Fincon -  4 Worker's

Work on patching interior bldg B, work on dock & dumpster enclosure walls, clean forms, layout on T.I., work on drain trenches  & clean up.

Highmark Elec - 2 Worker's

Work on bldg C interior power & clean up

ESP Excavation - 3  workers

Rough grade on east ponds, grade docks, move extra dirt, layout & clean up

Capitol Glass - 5 Worker's

Work on window frames in building B, start setting glass on south end, layout & clean up

Kimco - 4 Worker's

Work on fire lines in building C, load move & unload material, layout & clean up

Steerling Structures - 4 Workers

Work on framing north end of T.I.

            Weather -  Sunny  - High 89  Low 67



















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...