Monday, August 8, 2022

August 8 2022

                                              Daily Job Report


Fincon -  4 Worker's

Work on patching interior bldg B, work on dock & dumpster enclosure walls, clean forms, strip & clean up drain trenches, move material, clean floors for caulking in building B  & clean up.

Highmark Elec - 2 Worker's

Work on bldg C interior power & buildout & clean up

ESP Excavation - 3  workers

Rough grade on east ponds, grade docks, move extra dirt, layout & clean up

Capitol Glass - 5 Worker's

Work on window frames in building B, set glass on south end, layout & clean up

Kimco - 4 Worker's

Work on fire lines in building C & B, load move & unload material, layout & clean up

Steerling Structures - 4 Workers

Work on upper floor framing north end of T.I.

            Weather -  Sunny  - High 88  Low 69