Tuesday, September 20, 2022

September 16 2022

                                                          Daily Job Report


Fincon -  5 Worker's

Finish doors in East T.I., work on backing & framing, clean out docks, move conex's, scrub floors, work on east retaining wall & clean up.

Highmark Elec - 4 Worker's

Work on B & C interior T.I. power & clean up

Quiqksilver -  12 worker's

Work on pouring & finishing curb & gutter & clean up

ESP Excavation - 4  workers

Work on grading curb & gutter, work on dock paving, layout & clean up

Kimco - 2 Worker's

Work on fire sprinkler building B & clean up

Quality Fire - 2 Worker's

Work on fire alarms & strobes & clean up

UIS Paint - 2 Worker's

Work on east building west wall interior & clean up

            Weather - Sunny - High 86  Low 57























No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...